Hypercare is a dedicated support and stabilization period immediately following production go-live.

During this phase, the Client and R&T monitor settlement activity, validate reporting outputs, complete post-funding reconciliation activities, and ensure the DDM Program successfully transitions into ongoing operations.

Successful completion of Hypercare confirms operational readiness and supports the transition to Business-as-Usual (BAU) support.

Hypercare Approach

Hypercare begins immediately following successful production funding and continues through the initial stabilization period.

During this phase:

  • Settlement and reporting activities are closely monitored
  • Post-funding validation and reconciliation activities are completed
  • Users receive additional support and training, as needed
  • Production issues are identified and resolved
  • Knowledge transfer activities are completed

Once Hypercare Exit Criteria have been met, support transitions to the standard Business-as-Usual (BAU) support model.

Objectives

  • Monitor funding, settlement, and reporting workflows following go-live
  • Complete reconciliation and post-funding validation activities
  • Confirm integrations, file deliveries, and reports are operating as expected
  • Ensure business users are prepared to support day-to-day operations
  • Identify and resolve post-production issues
  • Prepare for transition to Business-as-Usual (BAU) support

Duration & Milestones

Hypercare generally lasts four (4) weeks following production go-live or until the Exit Criteria have been met.

Typical milestones include:

  • Completion of at least one full month-end processing cycle
  • Successful funding, settlement, and reconciliation activities without material exceptions
  • Validation of critical operational and client-facing reports
  • Completion of operational knowledge transfer activities

Key Activities

Monitoring & Validation

During Hypercare, settlement activity, file processing, reporting outputs, and reconciliation activities are monitored closely to ensure the DDM Program is operating as expected.

Activities may include:

  • Enhanced monitoring of settlement activity and file processing
  • Report validation
  • Reconciliation validation
  • Month-end settlement review activities

Client Action: Review reports, validate expected balances, and escalate discrepancies for investigation.


Issue Identification & Resolution

During the stabilization period, production issues and operational exceptions are reviewed and addressed.

Activities may include:

  • Review and resolution of client questions
  • Investigation of production issues
  • Resolution of operational exceptions

Client Action: Report issues promptly and provide supporting information needed for investigation.


User Support & Knowledge Transfer

Hypercare provides an opportunity to reinforce operational readiness and ensure business users are comfortable supporting daily program activities.

Activities may include:

  • User support and troubleshooting
  • Refresher training activities
  • Operational knowledge transfer

Client Action: Participate in training activities and confirm operational readiness.


Transition to BAU Support

As Hypercare activities conclude, ownership transitions from implementation-focused support to the standard support model.

Activities may include:

  • Preparation for ongoing operational support
  • Review of open issues and risks
  • Confirmation of support contacts and escalation paths
  • Transition planning with Client Services

Client Action: Review support processes and confirm appropriate contacts are identified for future support needs.

Roles & Responsibilities

Client

  • Monitor production activity and operational workflows
  • Validate reports and reconciliation outputs
  • Participate in training and knowledge transfer activities
  • Escalate issues and operational concerns
  • Confirm readiness to transition to BAU support

R&T Implementation Manager

  • Provide enhanced post-go-live support
  • Monitor production activity and settlement workflows
  • Investigate and resolve operational issues
  • Facilitate training and knowledge transfer
  • Coordinate the transition to BAU support

Exit Criteria

Hypercare may be formally exited when all of the following conditions have been met:

  • One complete month-end cycle has been successfully completed
  • Funding, settlement, reconciliation, and reporting processes are operating successfully in production
  • No Severity 1 (Critical) or Severity 2 (High) production issues remain open
  • No recurring production issues have been identified for five (5) consecutive business days
  • Required reports have been validated by designated business stakeholders
  • Operational support teams have received all required documentation, training, and system access
  • Knowledge transfer activities have been completed and acknowledged by the Client
  • Open risks and known issues have been reviewed and accepted by the Client

Successful completion of these activities confirms the program has stabilized and is ready to transition to Business-as-Usual support.

Post-Hypercare Support

Upon completion of Hypercare, all support requests, questions, incidents, and enhancement requests transition to the standard Business-as-Usual (BAU) support model.

Support Request Process

All post-Hypercare support requests should be initiated through Client Services.

Support requests should include:

  • Client name
  • Program name
  • Description of the issue or request
  • Relevant reports, file names, screenshots, or supporting documentation
  • Contact information for the requestor

Escalation Process

Client Services will:

  • Acknowledge receipt of the request
  • Coordinate resolution with the appropriate operational, technical, or product support teams
  • Provide status updates throughout the resolution process

Issues requiring additional attention may be escalated through established support management and leadership channels.

Support Ownership

Following Hypercare:

  • Client Services serves as the primary point of contact for support inquiries
  • Implementation resources are engaged through the established escalation process when required
  • Enhancement requests and future project work are evaluated through the standard change management process

What's Next